Design of factories: OSB Kronospan. Production Area.
Function: Delivery of the glue. Infill the glue tanks.

Description: Single story extension Glue preparation and Blending facility with steel frame of columns and beams. External walls — RC precast sandwich panels. Foundation — in-situ pile caps for frame columns with the RC precast driven piles. Floor slab — in-situ RC ground bearing slab.

Trenches and pits — in-situ RC

CLANCY ENGINEERING has completed design of the project stages as follows:

  • Concept;
  • Proekt;
  • Working documentation;
  • Author’s supervision.

Objects of design:

  • Pile foundation (RC precast driven piles);
  • RC pile caps for steel frame columns;
  • Precast RC plinth panels;
  • RC trenches and pits;
  • RC ground bearing floor slab.

Project Information

2013
1500 м2

Services

Specializations

Stages

    • Concept, Proekt, Working documentation complete.
    • Author’s supervision complete.

Architects

Client